The State of Missouri recently joined a majority of states allowing political subdivisions to make use of design-build and construction manager-at-risk contracts for public works projects. The new law, signed on July 1, 2016, permits political subdivisions (such as state agencies, counties, municipalities, school districts, hospital districts, and sewer districts) to utilize project delivery methods that are widely used in private construction projects.
Missouri political subdivisions (with some exceptions) are required to engage in traditional design-bid-build delivery of projects (i.e., the public body selects an architect based on qualifications, then picks the low-bidding contractor following completion of design). For more complex projects, public bodies could engage a construction manager, but the CM is not permitted to perform any construction or provide a price guarantee (this is commonly referred to as construction manager as agent).
The new statute allows political subdivisions to engage a construction manager-at-risk, where the contractor is engaged prior to completion of construction documents, provides preconstruction services for the owner during the design process, and typically provides a guaranteed maximum price or fixed price after the construction documents are complete. The new statute also permits design-build, where the contractor is responsible for both the design and construction of the project (and holds all of the design and engineering contracts). Public bodies now have increased flexibility in choice of delivery method, which they hope will result in time and cost savings for their projects.
Because the use of each construction method is only permitted under certain circumstances and procedures, we’ve created a chart that outlines the requirements of each construction method under the new statutes: Chart: Project Delivery Options Under New Missouri Statutes.
Design-Build (RSMo 67.5060) | CM At-Risk (RSMo 67.5050) | |
---|---|---|
Bidding |
Three Phases: |
Two Steps: |
Award |
Phase II: |
Qualifications: ≥ 40% of total points,Cost: ≤ 60% of total points |
Timing for Evaluation of Bids |
No requirement |
Evaluation and ranking of bids must occur within 45 days after date of opening the proposals or qualification submissions |
Publication of Request for RFP |
Newspaper of general circulation in the county where the political subdivision is located once per week for two consecutive weeks prior to opening proposals. |
Same |
Thresholds for Use ($) |
Civil Works: None |
Civil Works: > $2 Million |
Bid Stipend |
Amount set in RFP (not less than 0.5% of total project budget) must be paid by political subdivision to each prequalified design-builder whose proposal is responsive but not accepted; bidder provides nonexclusive license to use design submitted without any liability for use of such design |
None |
Sunset |
September 1, 2026 |
September,1, 2026 |
The full text of HB 2376 (2016) is available here.
NOTICE.
Although we would like to hear from you, we cannot represent you until we know that
doing so will not create a conflict of interest. Also, we cannot treat unsolicited
information as confidential. Accordingly, please do not send us any information
about any matter that may involve you until you receive a written statement from
us that we represent you (an ‘engagement letter’).
By clicking the ACCEPT button, you agree that we may review any information you transmit to us. You recognize that our review of your information, even if you submitted it in a good faith effort to retain us, and, further, even if you consider it confidential, does not preclude us from representing another client directly adverse to you, even in a matter where that information could and will be used against you. Please click the ACCEPT button if you understand and accept the foregoing statement and wish to proceed.